Elaboration of the project phase DE “Rehabilitation of frames and connections, including the rehabilitation of electrical circuits in SRA 1- 110kV”. Elaboration of the project phase DE “Own direct current services SRA 1”
Modernization of the 110/20/6.3kV Portile de Fier II (Ostrovu Mare) station: a. Upgrade of the PT Control Block. Finishing and related installations, including expertise of concrete frames and foundations b. Works required in accordance with the provisions of the regulations in force and as a result of the minutes and site dispositions drawn up during the execution
Execution/modernization of electrical installations, including energy evacuation circuits in the M.T. and PIF station according to the specifications of the Grivita CET and the tenders attached to the contract for:Objective A-T/G AKP 6MW Grivita CET; Objective B-T/G AKL 5.4MW Grivita CET